Direct Answer
**When the earthing resistance in mountainous/sandy-stone areas cannot reach the standard no matter what, which resistance-reduction measure should be used? The answer: first judge whether the high resistivity is in the shallow or deep layer — for a high-resistivity shallow layer, replace the soil and use resistance-reduction agents to improve the dissipation near the electrode; when a low-resistivity layer exists in the deep layer, a deep-well vertical earth electrode is more effective; earth modules suit places with limited space where the dissipation area must be enlarged. The choice depends on the soil layering and the site — the more expensive deep well is not always better.**
At a mountainous substation, the measured earthing resistance exceeded the limit; three deep wells were blindly drilled, costly and limited in effect — the wells still penetrated the high-resistivity rock. After a layered soil-resistivity test confirmed a high-resistivity sandy shallow layer and a low-resistivity groundwater deep layer, one deep well reaching the low-resistivity layer plus shallow replacement brought the resistance to standard at lower cost. **The key distinction: resistance reduction is not "the more expensive, the better" — test the layering first and choose by "whether the high resistivity is shallow or deep"; a deep well drilled in the wrong place wastes the money.**
Why:
- **Layering first**: measure the shallow/deep resistivity before deciding; - **Resistance-reduction agents**: improve the dissipation near the electrode (shallow); - **Earth modules**: enlarge the dissipation area (limited space); - **Deep-well earthing**: reaches the deep low-resistivity layer (effective when deep).
Key insight: **"Choose the measure by the soil layering: replacement/agents for the shallow, deep wells for the deep, modules when space is limited — test the layering before spending; a well in the wrong place wastes the money."**
At a park, the site was too constrained to spread a horizontal grid and the resistance never reached the standard; earth modules enlarged the dissipation area and it passed. **Lesson: the site constraint decides the measure — the deep well is not universal; when space is limited, modules plus agents are more practical.**
1. Test the Soil-Resistivity Layering First
Step one: is the high resistivity shallow or deep?
**Why layering matters**: - Shallow high resistivity → replacement/agents; - Deep low resistivity → a deep well penetrating; - Choosing the wrong measure wastes money; - Layering is the starting point of selection.
**The test method**: - The four-probe method measures the resistivity; - Different spacings measure different depths; - A resistivity-vs-depth curve; - Identifying the shallow/deep high-low.
**Reading points**: - Shallow high, deep low → a well is most effective; - High everywhere → replacement + a larger dissipation surface; - A local low layer → aim the well at it; - The test guides the scheme, not guesswork.
Key insight: **"Layer first, then reduce: the four-probe method gives the resistivity-vs-depth curve — see whether the high resistivity is shallow or deep, and the measure follows the layering."**
2. Resistance-Reduction Agents: Improving the Dissipation Near the Electrode
Step two: what to do about a shallow high-resistivity layer.
**The role of the agents**: - Wrapping the electrode and lowering the contact resistance; - Improving the dissipation near the electrode; - Enlarging the effective dissipation radius; - The first choice for a shallow high-resistivity layer.
**Applicable conditions**: - A shallow high-resistivity layer and the site allows excavation; - Poor dissipation near the electrode; - Combined with low-resistivity replacement; - The amount follows the electrode geometry.
**Notes**: - Choose long-lasting agents (prevent loss); - Avoid corrosion of the electrode; - Combine with the horizontal grid; - Monitor the effect regularly.
Key insight: **"Agents improve the dissipation near the electrode and enlarge the effective radius — first choice when the shallow layer is high-resistivity and excavatable; mind the durability and corrosion."**
3. Earth Modules: Enlarging the Dissipation Area
Step three: what to do about limited space.
**The role of the modules**: - Adding dissipation area in module form; - Replacing a spread grid when space is limited; - Combined with electrodes/grids; - Efficient dissipation.
**Applicable conditions**: - The site is too constrained to spread a horizontal grid; - The dissipation area must be enlarged; - Combined with agents/replacement; - Flexible vertical/horizontal layout.
**Notes**: - Reliable connections between modules; - Conducting to the main grid; - Burial depth matched to the environment; - Monitor the resistance-reduction effect.
Key insight: **"Modules enlarge the dissipation area when space is limited — when the grid cannot spread, use modules; combining with agents is more practical."**
4. Deep-Well Earthing: Penetrating to the Deep Low-Resistivity Layer
Step four: what to do about a deep low-resistivity layer.
**The role of the deep well**: - A vertical earth electrode penetrating the high-resistivity shallow layer; - Reaching the deep low-resistivity layer/groundwater; - Deep dissipation, a large drop in resistance; - Most effective when the deep layer is low-resistivity.
**Applicable conditions**: - A low-resistivity layer exists in the deep; - The shallow layer cannot be fixed by replacement; - The site allows vertical space; - Effective only when aimed at the low layer.
**Notes**: - Confirm the low-layer position by layering first; - A well in the wrong place has limited effect; - The depth/diameter match the geology; - Connected to the shallow grid.
Key insight: **"A deep well penetrates the high-resistivity shallow layer to the low-resistivity layer — but first confirm the low layer exists; a well in the wrong place wastes the money."**
5. Weighing the Measure against the Site and Cost
Step five: how to set the scheme comprehensively.
**The selection logic**: - Test the layering first; - Shallow high → replacement/agents; - Deep low → a deep well; - Limited space → modules.
**The cost trade-off**: - Deep wells are expensive and depend on the geology; - Agents/replacement are cheaper and suit the shallow; - Modules suit constrained sites; - A combined scheme is the best.
**Practice verification**: - Measure the resistance after construction; - Monitor online with the FR Earth-Resistance Monitor; - Recheck the seasonal variation; - Add measures when it still fails.
Key insight: **"Set the scheme by layering + site + cost: replacement/agents for the shallow, deep wells for the deep, modules when constrained — verify by measurement after construction."**
6. Product Implementation: Resistance Reduction and Monitoring as One
WeiWuLian products manage the resistance-reduction system:
- **FR Earth-Resistance Monitor**: online monitoring of the earthing resistance; - **Layered testing**: digitizing the soil resistivity; - **Effect recheck**: verifying after resistance reduction; - **Data loop**: reduction-monitoring-maintenance closed.
The design principle in one sentence: **"Test the layering, choose by the layer, verify after construction, measure online — manage the reduction system with data."**
7. Common Misjudgments
1. **"The more expensive the deep well, the better"**: ignoring the layering. Result: a well in the wrong place wastes money. Correct: test the layering first. 2. **"Use agents everywhere"**: ignoring the applicable conditions. Result: works shallow, fails deep. Correct: choose by the layer. 3. **"The deep well is universal"**: ignoring the site constraints. Result: cannot spread in a constrained site. Correct: combine modules. 4. **"Just do it without testing"**: ignoring the layering test. Result: the wrong measure. Correct: measure with the four-probe method first. 5. **"Done after construction"**: ignoring the effect verification. Result: a failure goes unnoticed. Correct: measure and monitor online.
Scope and Limitations
This article explains the resistance-reduction paths for high-soil-resistivity scenarios (layering first, and the applicable conditions and trade-offs of agents/earth modules/deep wells), applicable to selecting and understanding resistance-reduction schemes. The exact processes and parameters follow GB 50057-2010, related standards and the manufacturers' data; this article explains only the selection logic and judgment basis. All cases are anonymized (a mountainous substation, a park) and do not refer to any specific customer.